Loy Lake Road Phase 1
Owner: City of Denison, Texas
Project Type: Reconstruction
Contract Amount: $9,903,992.50
Completion Date: June 24, 2024
Description of Work:
· Remove Existing Concrete Pavement, Asphalt Pavement, Trees, Structures, Fence, & Utilities
· Temporary Asphalt Pavement – 6,734 SY
· Mass Excavation – 12,200 CY
· Subgrade Treatment: 6” Cement Treated Subgrade – 22,818 SY
· Concrete Pavement & Roundabout: 7” 3600 PSI Concrete – 17,566 SY
· Asphalt Pavement: 6” to 8” HMAC – 2284 SY
· Concrete Flatwork: 6” Concrete Sidewalk – 53,000 SF, 6” Concrete Driveway – 2,443 SY
· Storm Drain: 18” to 72” RCP – 4,693 LF
· Water Line: 8” to 12” PVC Waterline – 4,330 LF, Gate Valves: 44 EA, Services: 43 EA
· Sanitary Sewer: 8” PVC Sanitary Sewer – 2,045 LF, Services – 14 EA, Manholes – 9 EA
· Decorative Landscaping, Hardscape, & Irrigation
· Pavement Marking – 8,700 LF
· Street Light Conduit – 2,312 LF