Garland Naaman School Rd - City of Garland
Project Type: Reconstruction
Contract Amount: $28,777,787.80
Estimated Completion Date: March 2027
Description of Work:
EXCAVATION : 36000 CY
LIME & CEMENT STABILIZATION : 37,297 SY
12”-48” RCP : 6402 LF
6”-30” WATERLINE : 6275 LF
30” AWWA CL 250 Aerial Crossing – 313 LF
8”- 48” SANITARY : 5167 LF
3 SPAN BRIDGE
6” CL P1 Trail (12’-14’ Wide) – 4,596 SY
4” CL “C” Sidewalk (6’ Wide) – 2,913 SY
5” CL “C” Sidewalk – 40 SY
4000 PSI CL P1 Alley Paving (6 Alleys) – 1,944 SY
5” CL “P1” Driveway Pavement (19 Driveways) – 1,259 SY
6” CL “P1” Driveway Pavement (11 Driveways) – 2,772 SY
6” CL “P1” Street Pavement – 2,014 SY
7” CL “P1” Street Pavement – 553 SY
8” 4000 PSI CL “P1” Street or Driveway Pavement – 1,691 SY
10” 4000 PSI CL“P1” STREET PAVING : 29076 SY