Custer Pkwy Reconstruction (Campbell to SH 190)
Description of Work:
Remove Existing Trees, Structures, Fence, Traffic Signals, Signs & Utilities
Type D Temporary Asphalt Paving (2” Thick): 20,000 SY
Remove Concrete Pavement, Driveways, and Alley 65,000 SY Remove Concrete Sidewalk and Concrete Median - 5,556 SY
Excavation and Embankment - 9,000 CY
Subgrade Preparation (Scarify & Recompact 8”) - 62,000 SY
9” CL Reinforced Concrete Pavement (Hand Pour) - 53,000 SY
9” (HES) Reinforced Concrete Pavement - 1,000 SY
10” Reinforced Concrete Pavement - 3,500 SY
5” CL Reinforced Concrete Driveway (74 Driveways) - 2,400 SY
4” CL “A” Reinforcement Concrete Sidewalk - 5,333 SY
Stamped & Colored Concrete - 13,000 SF
6” PVC WL W/ Fittings – 965 LF
8” PVC WL W/ Fittings – 1800 LF
12” PVC WL W/ Fittings – 9,000 LF
Long Dom WS 2” Or Smaller by Bore w/ MTR Box - 70 EA
Short Dom WS 2” Or Smaller by Open Cut w/ MTR Box - 70 EA
Steel Encase for 12” WL by Open Cut – 40 LF
8” to 15” PVC SDR-26 Sanitary Sewer & Structures – 3,640 LF
8” to 10” HDPE Sanitary Sewer by Pipe Bursting – 3,100 LF
Long SS Lateral – Pipe Bursting Sub is installing service
Bore water and sewer line under the railroad.
18” to 54” CL III RCP & Structures – 1,100 LF
Install Street Signs & Striping
Install Traffic Signals
Install Street Lights
Install New Landscaping & Irrigation